J. wrote: “Any idea what’s going on with the fenced-in site on Harrison in front of Meadow Lane? [There is also one on the west side of Greenwich; see below.] It’s been sitting untouched for over a year and has been accumulating junk and trash. Plants growing in the Belgian block. City just dropped off some rat traps. Such an eyesore on one of our prettiest corners.”
So this an update on this post from last September. The fenced-in sites are central storage areas for the Department of Design and Construction’s *Complex* Pedestrian Ramp projects at 31 corners in Community Boards 1 and 2 — though these two sites only cover material for nine out of the 31 corners. The new corners will be ADA compliant, plus the contractors will reconstruct the curb and sidewalks; relocate water mains and hydrants; adjust catch basins, sewer manholes and chute connections; and add traffic lighting upgrades.
The Complex Ped Ramp projects, as opposed to the Simple Ped Ramp projects, require much more coordination because of existing underground interferences, the department said. The project will cost $21 million overall. It started in June 2025 and completion is expected in June 2027.
As of today, utility and street-light work should be completed by the end of the year, with concrete pedestrian ramp work beginning in the spring.
The community liaison for the project did tell me that they will speak with the contractor to see if the storage area on the west side of Greenwich Street can be reduced. (Not the one in front of Meadow Lane…) These sites, the department said, are the most central to all areas where the contractor is working.
Neighbors can contact Prakrati Shrivastava, the NYCDDC community construction liaison, at hwpr19mc1.ccl@gmail.com, phone 646-887-3909 or mobile 332-877-6520.
DDC has already started work at
Work is still pending:
Pam,
Thanks for highlighting this. This project is apparently a response to the city being sued by people falling in the cross walks with cobblestones, which DDC had contractors install in the first place back in 2011 and 2012. But the DDC instead of simply paving these areas, as was done in other locations, came up with a complex project of installing flat pavers, installing new light signals, and widening curb cuts. But DDC assumed that the sidewalks were on soil, which everyone knows, by just walking around, that most of our sidewalks are large stones sitting on vaulted sidewalks. So for over a year DDC has been working on changing this plan. Thats why its stalled. And DDC spending even more money than needed.